Understanding Liquidated Damages under Chinese Law: Key Points for Foreign Enterprises

In international business contracts governed by Chinese law, liquidated damages clauses are a common fixture. They set out pre-agreed compensation for breaches, helping both sides clarify rights and obligations while adding certainty to transactions. However, Chinese law places strict rules and judicial oversight on these clauses—rules that often differ from those in overseas common law or civil law systems. To help foreign businesses steer clear of pitfalls in cross-border deals, this article breaks down the key rules, statutory limits, court adjustment practices, and special scenarios for liquidated damages under Chinese law.
1. The General Rule for Liquidated Damages: Compensation-Oriented with Supplementary Punishment
The governing rule for liquidated damages in China is established by Article 585 of the Civil Code, which defines their primary purpose as compensating the non-breaching party for actual losses incurred due to a breach of contract. Punishment is explicitly characterized as a secondary, supplementary function. This compensation-oriented foundation distinguishes China’s legal approach from common law systems, where parties may independently agree upon high punitive liquidated damages.
In practice, this principle requires that the contractually agreed amount of liquidated damages bears a reasonable relationship to the foreseeable or actual loss. Should the stipulated sum of liquidated damages be judged substantially excessive or overly low compared to the proven loss, the court is empowered by law to adjust it upon request. This judicial discretion serves to prevent outcomes where the non-breaching party obtains a windfall gain from liquidated damages, or where the breaching party bears a liability disproportionate to the harm caused.
Consequently, when drafting or enforcing contracts within China’s jurisdiction, parties should focus on establishing a credible pre-estimate of potential loss. Well-structured liquidated damages clauses that demonstrate this compensatory intent are more likely to be upheld and enforced by Chinese courts.
2. Liquidated Damages: Understanding the 30% Statutory Cap for “Excessively High” Claims
When navigating contract disputes involving liquidated damages in China, grasping the judicial benchmarks governing liquidated damages is critical for drafting enforceable contracts and resolving disputes effectively.
According to the Supreme People’s Court’s Minutes of the National Court Work Conference on the Implementation of the Civil Code, liquidated damages are generally deemed “excessively higher than the losses caused” if they exceed 30% of the actual losses defined under Article 584 of the Civil Code. This 30% threshold serves as a core reference for adjusting liquidated damages: courts or arbitration tribunals are empowered to reduce any portion of aliquidated damages claim that surpasses this cap. This rule delivers critical clarity for liquidated damages clauses in contract drafting and dispute resolution, safeguarding legal interests while upholding the enforceability of contract terms tied to liquidated damages.
It is important to note that the “actual losses” used to evaluate liquidated damages include expected benefits that would have been secured upon full contract performance, but shall not exceed the scope of losses foreseeable by the breaching party at the time of contract conclusion. This definition directly shapes how liquidated damagesare calculated and adjusted in practice.
For disputes involving late payments or contracts with financing elements (e.g., cross-border loans, equity repurchase agreements, investment valuation adjustment mechanisms), courts typically set aside the 30% rule and instead use private lending interest rate benchmarks to adjust liquidated damages.
Currently, the widely accepted standard for such liquidated damages adjustments is four times the one-year Loan Prime Rate (4xLPR) announced by the National Interbank Funding Center, translating to an annual rate of approximately 14.4%-15% in 2026. For contracts signed prior to August 20, 2020, some cases may still reference the old 24% annual benchmark. Critically, the total sum of liquidated damages, interest, service fees, and other related charges cannot exceed this upper limit—and any excess amount already paid can be claimed back by the affected party.
3. Judicial Adjustment of Liquidated Damages: Key Factors & Binding Rules
The judicial adjustment of liquidated damages follows the principle of party-initiated application, but courts are not entirely passive in practice. Even if the breaching party does not file a request to adjust liquidated damages, if the court determines that the agreed liquidated damages are excessively high, it may take the initiative to adjust liquidated damages ex officio. A representative case is (2022) Yue 01 Min Zhong No. 6068, where the Guangzhou Intermediate People’s Court adjusted the agreed daily liquidated damages rate of 3% (equivalent to an annualized rate of over 1000%) to the Loan Prime Rate (LPR) plus 50%—even in the absence of the defendant. This ruling fully reflects the judicial logic governing the adjustment of liquidated damages.
When adjusting liquidated damages, courts will comprehensively assess multiple core factors:
Progress of contract performance: For example, partial performance of the contract will lead to a corresponding reduction of liquidated damages;
Degree of fault of the breaching party: Malicious breach may not warrant a reduction of liquidated damages;
Industry practices and transaction background: These contextual factors help courts determine a reasonable level of liquidated damages aligned with market norms.
Additionally, a critical reminder: Even if parties include a clause in the contract stating they “waive the right to adjust liquidated damages,” such an agreement may be deemed invalid by courts. Judicial practice consistently supports adjusting liquidated damages based on actual circumstances to balance the legitimate interests of both parties.
4. Burden of Proof Allocation for Liquidated Damages
The party claiming that liquidated damages are excessively high and requesting a reduction bears the primary burden of proof. Specifically, this party must demonstrate that the agreed-upon liquidated damages exceed the scope of actual losses caused by the contract breach.
When the non-breaching party argues that the stipulated liquidated damages are reasonable, it is also required to provide corresponding evidence to verify the amount of its losses. Such evidence may include capital occupation costs, rights protection expenses, expected interest losses, and other quantifiable losses that support the reasonableness of the set liquidated damages.
If neither party can fully adduce sufficient evidence to substantiate their claims regarding liquidated damages, the court will exercise discretion to determine a reasonable amount of liquidated damages based on the specific facts of the case and prevailing industry standards.
5. Conclusion: Professional Guidance to Mitigate Liquidated Damages Risks in Foreign-Related Transactions
When conducting foreign-related transactions, liquidated damages risks stand as a major threat to your business’s financial security and legal rights—and navigating these risks requires targeted professional support.
China’s liquidated damages system diverges significantly from frameworks in other jurisdictions. Inadequate drafting of liquidated damages clauses, paired with limited familiarity with Chinese judicial practices around liquidated damages, can easily result in unintended rights erosion and substantial financial losses.
Our team specializes in foreign-related contract disputes, with deep mastery of the critical differences between Chinese and international liquidated damages rules. We offer full-cycle professional assistance: from crafting enforceable liquidated damages clauses to providing strategic guidance during dispute resolution, we help you avoid legal pitfalls tied to liquidated damages and robustly safeguard your core commercial interests.
If you have questions about liquidated damages in foreign-related transactions or need tailored legal support to mitigate associated risks, feel free to contact us at any time.
Contacts:
Saway Wang
Tel: +86 18017682422
Email: sawaywang@billionslawyer.com

Read More